Project Implementation
Regulation 24 - Commencement of Project
A project proponent shall commence the implementation of an approved carbon project within twelve (12) months from the date of issuance of the Letter of Approval by the Designated National Authority.
Implementation Timeline
Letter of Approval Issued
February 20, 2025
Commencement Deadline
February 20, 2026 (12 months)
9 months remaining
Declare Project Commencement
Once you have commenced project activities, please declare the commencement date below. This declaration is required per Regulation 24 and must be submitted to the DNA within 14 days of project commencement.
Select the date when project activities officially commenced
Commencement Criteria
Physical construction or installation has begun
Project equipment has been delivered to site
Community engagement activities have started
Baseline monitoring has commenced
Notifications
Kilifi Solar Project
You have 9 months remaining to commence project activities per Regulation 24.